DOORS OPENED IN 2022!
Project Progress
The slideshow recaps construction highlights and milestones since groundbreaking in June 2020.
June 2021 - Window installation complete
June 2021 - New windows in west wall
April 2021 - Roof sub-layers complete
February 2021 - Spring mud, Methow style!
April 2021 - Hoisting the energy recovery ventilator (ERV)
February 2021 - FOWL Board of Directors visit
January 2021 - Truss action
January 2021 - Placing the last roof truss
January 2021 - Framing the west wall
December 2020: Beam action at future patio
December 2020 - Beams were precisely set
December 2020 - First walls are framed
November 2020 - Successful winter concrete pour
September 2020 - Creating the footings
September 2020 - Little Star students watch the concrete action
September 2020 - Team Tuesday meets every week to manage the project
July 2020 - Excavation ready!
July 2020 - Sprinkling the site for excavation
June 2020 - Groundbreaking!